The wind farm is scheduled to be ready for production during the second half of 2013, at which time it will produce about 86,500 MWh annually.
Construction work in progress in the Dingle-Skogen Vind wind farm, comprising 14 wind turbines
Rabbalshede Kraft has i May, 2012, entered into an agreement with the Gothenburg Diocese concerning transfer of two turbines, press release>>
An agreement was signed with Enercon concerning the delivery of 14 2.3-MW wind turbines.
Ground work in cooperation with NCC, which is responsible for the construction of roads. A total of 14 kilometers of road will be constructed within the wind farms.
Fortum is the network owner in the area and has the assignment of laying cables and expansion of switchgear.